Can Nitin Gadkari fix the Highway crisis of India? : Economic Case study
Think School
15m 52s
Project Overview & Initial Promises
- Bharatmala launched July 31, 2015 by Indian government
- Large-scale highway project to fix India's logistical challenges
- Promised to eliminate highway congestions, connect tier 2/3 cities
- Original completion target: 2022
- Original budget: 5.35 lakh crores
Current Project Status & Cost Escalation
- Project delayed by 6 years to 2028
- Cost increased from 5.35 lakh crores to 10.63 lakh crores (100% increase)
- Cost increase equivalent to:
- 7x profit of Reliance Industries
- 19x profit of Tata Industries
- Entire 2020 defense budget
- Only 23% completion as of July 2022
Infrastructure Challenges Addressed
- Three major road system problems:
- Heavy traffic areas with only 1-1.5 lane roads
- Irregular lane sizes (4-lane suddenly becoming 2-lane, then back to 4-lane)
- Poor economic optimization - major corridors/ports not connected to hinterland
- 191 identified choke points where national highway merges with local traffic
- Bottlenecks during peak hours increasing accident risks
Project Specifications
- Cabinet Committee on Economic Affairs (CCEA) approved construction
- Cost: 15.4 CR rupees per kilometer
- Target: 26,000 km of economic corridors development
- Goals:
- Increase vehicle speed by 25% on national highways
- Decrease supply chain cost from 18% to 6%
- Connect multimodal logistics parks
Cost Escalation Factors
Land Acquisition Issues
- Originally budgeted at 30,000 CR
- Cost increased 5x due to delays
- 70-80% of landlords need convincing/negotiation
- Rehabilitation and formalities take months to years per patch
- Land prices increase during acquisition delays
General Inflation Impact
- 45% inflation from 2015-2023
- 1 km road cost: 10 CR (2015) → 14.5-15 CR (2023)
- Per 100 km stretch: 450 CR increase
- For 30,000 km: 1.35 lakh crores additional cost
Debt Burden Crisis
- NHAI external borrowings shot up significantly
- Interest growing faster than toll collections
- Government unable to pay back loans or even interest
- NHAI instructed to stop external borrowings for FY23-24
Funding Solutions & Methods
Securitization of Future Toll Revenues
- Government raises money upfront using future toll revenue as collateral
- Investors paid back through toll collections after highway completion
- NHAI monetized only 10% of 1.6 lakh CR target in first 2 years
Infrastructure Investment Trusts (InvITs)
- Investment instruments for infrastructure projects
- 90% of asset profits distributed to investors annually
- 10% kept for maintenance and growth
- 2021: NHAI launched InvIT with Canadian Pension funds (Ontario Limited, CBP Investments)
- SBI Infrastructure Fund also participated
- Raises concerns about foreign ownership of infrastructure
Toll Operate Transfer (TOT) Contracts
- Investor provides capital upfront
- Operates and collects revenues for specific time period
- After contract period, NHAI regains ownership
- NHAI awarded 6 TOT bundles, raised 26,366 crores
Key Concerns & Questions Raised
- Delays causing cascading effects on national economy
- Land acquisition remains biggest development hurdle
- Need for land bank solutions like Gujarat model
- NHAI's financial recovery plan unclear
- Further delays will waste more taxpayer money
- Citizens need to hold government accountable for project execution