ToolGauge Facility Overview
- 80,000 square foot facility in Tacoma, Washington
- Built primarily to support Boeing aircraft manufacturing
- Unfinished space intended for parts prep before enclosed paint booth
- Hundreds of parts per single aircraft wing
Aviation Industry Crisis Context
- Boeing delivered only 28 aircraft in Q3 (dramatic drop)
- Most destructive event for entire industry since 9/11
- 9/11 described as "blip on radar screen" compared to pandemic impact
- Boeing shed 19,000+ workers
- Thousands laid off across travel industry
- Further federal aid uncertain, more aerospace layoffs expected
Pre-Pandemic Challenges
- Boeing 737 MAX crisis began before COVID-19
- Two fatal crashes led to MAX grounding March 2019
- Initially expected months-long grounding extended over a year
- Production halt of MAX in January created backlog of finished jets
- Major suppliers responded with cuts
COVID-19 Impact on Travel
- Passenger volumes plummeted March 2020 due to lockdowns/travel restrictions
- April volumes down 95% compared to previous year
- International travel restrictions hurt wide-body aircraft demand
- All aircraft programs affected - "nothing was safe for supply chain"
Boeing Production Rate Changes
- 2019: Produced 750 aircraft
- 2020 forecast: Around 240 planes
- Pre-2020: 14 787s and 5 777s per month
- Post-COVID cuts: 6 787s and 2 777s per month planned for next year
- MAX production increase delayed until 2022
ToolGauge Business Profile
- 75% of business direct to Boeing or tier-one suppliers
- Specializes in wide-body aircraft parts (787, 777X engines)
- 40+ year relationship with Boeing - never lost contract
- Built business year-over-year through contract renewals/expansions
ToolGauge Crisis Response
- June layoffs: 190 employees reduced to 80
- Shift changes: From three 8-hour shifts to one 10-hour shift
- Business closed Fridays
- Employees assumed multiple roles
- Scheduling/production planning expanded to customer service, assembly, machining
Recovery Signs and Outlook
- Slowly ramping up production
- Rehiring laid-off workers (not hiring new)
- Optimism based on:
- Pending MAX return to service
- Expected travel recovery with vaccine availability
Industry Recovery Projections
- ToolGauge estimate: 1.5-2 years to pre-COVID production rates
- Boeing projection: 3 years for travel to return to 2019 levels
- Some analysts pessimistic: Recovery not until 2024, full recovery end of decade
- Boeing forecast: Pandemic reduces global jetliner demand by 2,000 planes over next decade
Strategic Adaptations
- Deferring planned investments in new facility
- Seeking complementary work outside commercial aerospace
- Revenue growth curve flattened for next 2 years before expected uptick
- Long-term investment approach maintained despite uncertainty