How to Build a $100 Million Satellite
How to Build a $100 Million Satellite
Wendover Productions
Wendover Productions
Company Overview & Satellite Market
- 4,708 satellites currently orbiting Earth from various providers
- Hundreds of satellites passing overhead at any given time
- Functions: GPS, Earth imaging, communications, government surveillance
- Tennis ball-sized Hubble chunk worth $1,500
- Modern commercial satellites cost hundreds of millions of dollars
- SSL (Palo Alto, California) - commercial satellite manufacturer owned by Maxar Technologies
- Clients: DirectTV, national governments, satellite TV/radio/internet providers
Customer Acquisition & Pricing
- Initial contact: phone call to SSL
- Cost range: tens of millions to several hundred million dollars depending on type and destination
- Process: back-and-forth negotiations between SSL and customer
- Customer specifies satellite requirements, SSL provides pricing
- Contract signing follows successful negotiations
Case Study: Telstar 19 Vantage Project
- Customer: Telesat (global satellite company headquartered in Canada)
- Purpose: additional capacity over busy North Atlantic region
- Sister satellite: Telstar 18 Vantage (launched August 2018)
- Service area: Asia and Oceania data services
- Record: heaviest commercial communication satellite at 15,600 pounds
- Service life: 15 years
Design Process
- Designers pull generic aspects from previous projects
- Modify designs for specific job requirements
- Process duration varies based on satellite complexity
- Parts ordering begins once design is locked
Component Manufacturing Strategy
- SSL builds ~50% of components in-house
- Orders remaining 50% from external suppliers
- Decision factors: performance requirements and SSL capabilities vs. supplier capabilities
- Example: SSL builds custom antenna reflectors
- Direct signals to Earth
- Custom-designed for specific coverage regions
- Photogrammetry dots for quality control verification
- Cameras photograph dots to ensure design accuracy
Assembly Timeline & Process
- 9-15 months: component delivery period
- Major elements assembled separately by different groups:
- Propulsion systems and framework
- Payload (cameras or communication systems)
- Solar panels (superlight and efficient)
- Several months: major component assembly
- Additional months: integration of major components together
Testing Procedures
- Each component tested independently before and during installation
- Rigorous whole-satellite testing phase
- Three major threat factors: vibration, temperature, sound
Vibration Testing
- Simulates launch vibration loads in X, Y, Z directions
- Shaker table testing
- Tests last 60-90 seconds (duration of launch vibration until upper atmosphere)
- Telstar 19 Vantage shown undergoing vibration testing
Thermal Vacuum Testing
- "Blue pumpkin" thermal vacuum chamber
- Simulates space vacuum (10^-5 torr)
- Tests payload and satellite components under vacuum
- Thermal panels simulate hot/cold environments:
- Hot: satellite facing sun
- Cold: satellite in Earth's eclipse shadow
- Ensures proper functioning in space conditions
Acoustic Testing
- Launch acoustic energy can damage satellites
- Speakers bombard satellite with acoustic energy
- Simulates loud launch environment
Transportation to Launch Site
- Customer selects launch provider: SpaceX, United Launch Alliance, Arianespace, others
- Destinations range from Vandenberg Air Force Base (4-hour drive) to Baikonur Cosmodrome, Kazakhstan
- Specialized shipping containers for transport
Domestic Transportation
- Truck transport with:
- Trusted oversized vehicle drivers
- Lead vehicle checking obstructions
- Trailing vehicle monitoring
- Motor home for driver rotation on long drives
International Transportation
- Antonov cargo plane for overseas sites
- Destinations: French Guiana, Kazakhstan, Cape Canaveral
Launch Site Selection Logic
Polar Orbits (North-South)
- Require launch sites with open water north/south
- Safety and rocket stage recovery considerations
- SpaceX uses Vandenberg AFB (Pacific Ocean south)
Geosynchronous Orbits (West-East)
- Launch in same direction as satellite orbit
- Vandenberg unusable (land to east)
- SpaceX uses Cape Canaveral (Atlantic Ocean east)
- Telstar 19 Vantage: geosynchronous orbit for consistent service area coverage
Pre-Launch Preparation
- Satellite arrives minimum 1 month before launch
- Additional testing to verify no transport damage
- Fueling and rocket mounting
- SSL monitoring during countdown with launch confirmation points
Launch Details: Telstar 19 Vantage
- Date: July 22, 2018, 1:50 AM
- Vehicle: SpaceX Falcon 9 from Cape Canaveral
- Flight path: southeast over Africa
- Deployment: 32 minutes 40 seconds post-launch, 358 miles above Mozambique
- Record: heaviest commercial communication satellite ever entered into service
Post-Launch Operations
- SSL establishes satellite communications immediately after deployment
- Command satellite into safe position
- Deploy solar arrays for power generation
- Activate all satellite systems
- 10-day orbit raising process: 350 miles to 22,000 miles altitude
- 2-4 weeks additional testing
- Final handover to customer (Telesat) for commercial operations