How to Build a $100 Million Satellite

How to Build a $100 Million Satellite

Wendover Productions

Wendover Productions

Company Overview & Satellite Market

  • 4,708 satellites currently orbiting Earth from various providers
  • Hundreds of satellites passing overhead at any given time
  • Functions: GPS, Earth imaging, communications, government surveillance
  • Tennis ball-sized Hubble chunk worth $1,500
  • Modern commercial satellites cost hundreds of millions of dollars
  • SSL (Palo Alto, California) - commercial satellite manufacturer owned by Maxar Technologies
  • Clients: DirectTV, national governments, satellite TV/radio/internet providers

Customer Acquisition & Pricing

  • Initial contact: phone call to SSL
  • Cost range: tens of millions to several hundred million dollars depending on type and destination
  • Process: back-and-forth negotiations between SSL and customer
  • Customer specifies satellite requirements, SSL provides pricing
  • Contract signing follows successful negotiations

Case Study: Telstar 19 Vantage Project

  • Customer: Telesat (global satellite company headquartered in Canada)
  • Purpose: additional capacity over busy North Atlantic region
  • Sister satellite: Telstar 18 Vantage (launched August 2018)
  • Service area: Asia and Oceania data services
  • Record: heaviest commercial communication satellite at 15,600 pounds
  • Service life: 15 years

Design Process

  • Designers pull generic aspects from previous projects
  • Modify designs for specific job requirements
  • Process duration varies based on satellite complexity
  • Parts ordering begins once design is locked

Component Manufacturing Strategy

  • SSL builds ~50% of components in-house
  • Orders remaining 50% from external suppliers
  • Decision factors: performance requirements and SSL capabilities vs. supplier capabilities
  • Example: SSL builds custom antenna reflectors
    • Direct signals to Earth
    • Custom-designed for specific coverage regions
    • Photogrammetry dots for quality control verification
    • Cameras photograph dots to ensure design accuracy

Assembly Timeline & Process

  • 9-15 months: component delivery period
  • Major elements assembled separately by different groups:
    • Propulsion systems and framework
    • Payload (cameras or communication systems)
    • Solar panels (superlight and efficient)
  • Several months: major component assembly
  • Additional months: integration of major components together

Testing Procedures

  • Each component tested independently before and during installation
  • Rigorous whole-satellite testing phase
  • Three major threat factors: vibration, temperature, sound

Vibration Testing

  • Simulates launch vibration loads in X, Y, Z directions
  • Shaker table testing
  • Tests last 60-90 seconds (duration of launch vibration until upper atmosphere)
  • Telstar 19 Vantage shown undergoing vibration testing

Thermal Vacuum Testing

  • "Blue pumpkin" thermal vacuum chamber
  • Simulates space vacuum (10^-5 torr)
  • Tests payload and satellite components under vacuum
  • Thermal panels simulate hot/cold environments:
    • Hot: satellite facing sun
    • Cold: satellite in Earth's eclipse shadow
  • Ensures proper functioning in space conditions

Acoustic Testing

  • Launch acoustic energy can damage satellites
  • Speakers bombard satellite with acoustic energy
  • Simulates loud launch environment

Transportation to Launch Site

  • Customer selects launch provider: SpaceX, United Launch Alliance, Arianespace, others
  • Destinations range from Vandenberg Air Force Base (4-hour drive) to Baikonur Cosmodrome, Kazakhstan
  • Specialized shipping containers for transport

Domestic Transportation

  • Truck transport with:
    • Trusted oversized vehicle drivers
    • Lead vehicle checking obstructions
    • Trailing vehicle monitoring
    • Motor home for driver rotation on long drives

International Transportation

  • Antonov cargo plane for overseas sites
  • Destinations: French Guiana, Kazakhstan, Cape Canaveral

Launch Site Selection Logic

Polar Orbits (North-South)

  • Require launch sites with open water north/south
  • Safety and rocket stage recovery considerations
  • SpaceX uses Vandenberg AFB (Pacific Ocean south)

Geosynchronous Orbits (West-East)

  • Launch in same direction as satellite orbit
  • Vandenberg unusable (land to east)
  • SpaceX uses Cape Canaveral (Atlantic Ocean east)
  • Telstar 19 Vantage: geosynchronous orbit for consistent service area coverage

Pre-Launch Preparation

  • Satellite arrives minimum 1 month before launch
  • Additional testing to verify no transport damage
  • Fueling and rocket mounting
  • SSL monitoring during countdown with launch confirmation points

Launch Details: Telstar 19 Vantage

  • Date: July 22, 2018, 1:50 AM
  • Vehicle: SpaceX Falcon 9 from Cape Canaveral
  • Flight path: southeast over Africa
  • Deployment: 32 minutes 40 seconds post-launch, 358 miles above Mozambique
  • Record: heaviest commercial communication satellite ever entered into service

Post-Launch Operations

  • SSL establishes satellite communications immediately after deployment
  • Command satellite into safe position
  • Deploy solar arrays for power generation
  • Activate all satellite systems
  • 10-day orbit raising process: 350 miles to 22,000 miles altitude
  • 2-4 weeks additional testing
  • Final handover to customer (Telesat) for commercial operations