Lessons from Intel's First Foundry
Lessons from Intel's First Foundry
Asianometry
Asianometry
Intel's Crown Jewels and Strategic Motivation (2000s)
- Intel identified two crown jewels: leading-edge manufacturing tech and x86 architecture
- Manufacturing leadership: 1-2 generation lead over competitors through technical choices
- Gate Last vs Gate First method (backed by IBM)
- TSMC initially pursued Gate First before abandoning
- Rising fab costs threatened sustainability with PC market revenues alone
- Strategic response: aggregate external customer demand to fund next nodes
- Paul Otellini sold XScale to Marvell (2006) to focus on x86
- Otellini's 2007 Financial Times interview: "entire internet coded for x86 base"
- iPhone proved x86 mobile strategy incorrect, rushed Intel Atom development
Custom Intel Architecture Foundry Launch (2008)
- Original name: Custom Intel Architecture Foundry (CIAF)
- Goal: monetize manufacturing + defend Intel Architecture franchise
- Small team formed for "turnkey custom foundry services"
- Initial VP left, replaced by Sunit Rikhi (Technology & Manufacturing VP)
- Rikhi served as general manager for 7 years
Building Foundry Capabilities
- Intel's processes optimized for x86 CPUs only, not external customers
- Pizza kitchen analogy: specialized for "pepperoni" (x86), needed flexibility for various "pizza types"
- Required extensive work to match TSMC/UMC/GlobalFoundries capabilities
- Needed complementary IP ecosystem (analogous to pizza toppings)
- TSMC had 3+ decades of foundry experience vs Intel's startup effort
Abandoning Intel Architecture Focus (2009)
- Parallel effort: Intel-TSMC alliance for Atom IP licensing
- Both initiatives failed due to low customer demand
- Atom ecosystem immaturity vs established ARM platform
- Otellini reluctantly dropped "Intel Architecture" from name (2009)
- Became "Intel Custom Foundry" (ICF)
- Otellini maintained belief ICF should focus on Intel Architecture
Competitive Constraints
- Major issue: competing with potential customers (AMD, Nvidia, Qualcomm)
- TSMC's charter: never compete with customers
- Intel chose slow, discreet rollout
- Restricted to non-competitive areas only
- Focused on Field-Programmable Gate Arrays (FPGAs)
- CFO Stacy Smith (2010): "not building broad-based foundry"
Early Customer Acquisition
- Target customers: startups tired of TSMC dependence
- Structured contracts with severe IP protection penalties
- First Process Design Kits: 32nm, quickly switched to 22nm
- First customer: Achronix (FPGA startup, Oct 2010)
- 1% capacity allocation of 22nm FinFET
- CEO: "Intel far ahead of anyone else in new process generations"
- Additional customers: Tabula (Feb 2012), Netronome (Apr 2012)
- All customers previously used TSMC nodes
22nm FinFET Technology Leadership
- Intel's 22nm with Tri-Gate FinFETs (late 2011)
- Decade of development to master FinFET manufacturing
- Ivy Bridge CPUs: scheduled Apr 2012, shipped June 2012
- Achronix Speedster22i FPGAs: volume production early 2013
- 50% power consumption vs competitors (Altera, Xilinx)
- Competitors limited to TSMC 28nm (volume-constrained)
- Intel 1-2 generations ahead
Design-Manufacturing Integration Strategy
- Mark Bohr (Oct 2012): "traditional foundry model running into problems"
- Intel's IDM advantage: design and process development under one roof
- Full service offering: wafer fab + design + advanced packaging
- Embedded Multi-die Interconnect Bridge: Intel innovation for foundry customers
- Reality: internal kingdoms struggled to collaborate
- Technology group resistance to customer feedback
- Product group worried about competitive comparisons
Internal Organizational Challenges
- Many Intel employees viewed ICF as waste of money/distraction
- Product group concerns about external CPU performance comparisons
- Technology group initially supportive, then withdrew support
- ICF struggled to get internal cooperation for customer requests
- Technology R&D extremely secretive, refused customer insights
- Resisted transistor modifications along power-performance curve
- Mark Bohr brought in to leverage senior management for R&D cooperation
Major Customer Win: Altera (2013)
- FPGA market dynamics: Altera (TSMC customer) vs Xilinx (UMC customer)
- UMC decline: 65nm node issues delayed Xilinx products
- Xilinx defected to Samsung + TSMC (Feb 2010)
- TSMC gave Xilinx 28nm access to win over Samsung
- Altera needed technical advantage, turned to Intel
- Altera deal: 14nm node production, trailing edge at TSMC
- CEO John Daane: "Intel's 14nm is second generation FinFET"
- TSMC shock: Morris Chang earnings call (Apr 2013)
- "I really hate to lose even part of old customer"
- "Intel very serious competitor to our customers"
14nm Node Challenges and Expansion
- Additional customers: Panasonic, LG for system-on-chips
- Altera design delay: resources consumed by TSMC 20nm Arria 10
- Intel 14nm node: 1 year late due to aggressive technology definition
- Originally scheduled 2013, reached high volume mid-late 2014
- Missed 2-year Moore's Law cadence
- Delay allowed TSMC/GlobalFoundries-Samsung to close gap
- Final node: second-gen FinFET, denser than TSMC 16nm first-gen
Apple Negotiations and 10nm Disaster
- Apple-Intel meetings (2013) for A9 dual-sourcing
- Apple rejected 14nm, interested in 10nm (due 2016)
- 10nm would have been 2 years ahead of TSMC N7
- A9 deal went to Samsung instead
- Intel 10nm problems: 50% area shrink, 2.7x transistor density increase
- Parallel development teams: 14nm issues discovered too late for 10nm
- Cobalt deposition tools not ready, EUV unavailable until 2019
- "50-story skyscraper with inadequate foundations" - complete restart needed
- 10nm delays (2015) dried up foundry business backlog
- 10nm Intel chips finally shipped 2019, foundry already dissolved
The Fatal Altera Acquisition (2015)
- Intel acquired Altera for $16.7 billion (June 2015)
- CEO Brian Krzanich strategy: integrate FPGAs into data center CPUs
- Goal: offload workloads to FPGAs instead of GPUs
- Integration work too complex, strategic product never shipped
- Disaster for ICF: acquiring marquee customer sent bad message
- Potential customers (Qualcomm) feared Intel would acquire them too
- Reinforced Morris Chang's competition concerns
Dissolution and End (2015-2018)
- Combination: Altera acquisition + 10nm failure = crippling
- Sunit Rikhi retirement (2015) after 8 years as GM
- Replacement favored Technology group over customer advocacy
- Customers worked directly with Technology, cutting out ICF
- Division employment: 1,100+ people worldwide at peak
- Quiet dissolution by 2018
- Book of business: 10+ customers, $1 billion+ contracted revenue
Lessons for Intel Foundry Services
- Pat Gelsinger mistake: rebuilding from scratch vs learning from ICF
- ICF achievements: real competitive threat to TSMC per Morris Chang
- Key takeaways:
- Organizational support needed across entire company
- Foundry needs autonomy to modify technology
- Leading-edge node is primary customer draw
- 18A/14A must work for foundry customers, not just CPUs
- Long-term commitment required (10+ year endeavor)
- Humility essential: ICF's ragtag nature was strength
- Study Morris Chang's foundry business philosophy