Introduction to Offshore Wind Turbines
- Observed wind turbines on ocean platforms while traveling to Taichung, Taiwan
- Taiwan developing offshore wind energy as renewable source
- Video covers growing offshore wind industry
Advantages of Offshore Wind Placement
- Higher wind speeds: Coastal areas windiest places globally, higher average speeds with less turbulence
- More space: Much more space offshore vs onshore
- European development: Population-dense European countries found difficulty locating suitable onshore sites for large-scale wind farms
- Larger turbines: Offshore locations allow wider turbine blades, offering scale advantages (similar to semiconductor fabs)
- Reduced opposition: Local neighbors complain about onshore wind farms' appearance/sound, offshore placement reduces (not eliminates) this issue
Historical Development
- 1930s: Offshore wind farm concept originated
- 1972: Dr. William Heronimus (naval architect, University of Massachusetts Amherst) first proposed floating wind turbine for electricity/hydrogen production
- Government studies initially discarded idea due to challenges
- 1991: First offshore wind farm operational in Denmark
- Danish energy context:
- Used wind energy for centuries
- Through 1960s: 90% reliant on fossil fuels imported from Middle East
- 1970s energy crisis prompted government support for modern wind industry
- 1976: Feed-in tariffs introduced
- Later: R&D subsidies for better wind technologies
Wind Turbine Technology Fundamentals
- Design goals:
- Capture maximum wind energy, convert to electricity
- Protect from damage (violent winds, extreme conditions)
- Power equation: Power intercepted proportional to:
- Air density (cold air denser than hot air)
- Blade swept area
- Cube of wind speed (most crucial factor)
- Scaling relationship: Wind speed doubles → intercepted power increases 8x
- Safety systems: Generators have cut-out limits for high wind speeds to prevent power surges/damage
- Intercepted vs generated power: Turbine limited in electricity generation from intercepted power
Turbine Configuration
- Modern standard: Large horizontal axis wind turbines (HAWTs) with 3 blades
- Horizontal axis: blades mounted parallel to ground
- Vertical axis turbines (VAWTs):
- Advantages: always face wind, gearbox/generator closer to ground
- Disadvantages: cannot turn away from wind (damage/surge risk), blade creates downward turbulence affecting neighbors
- Three-blade configuration: Optimal balance of cost, performance, long-term reliability, aesthetics
Offshore Installation Challenges
- No standard offshore wind turbine installation
- Unique factors: water depth, rotor size, foundation type
- Foundation options:
- Monopile: 3-8 meter wide poles driven into seabed
- Best for: 20-40 meter water depths, hard to semi-hard seabed
- Gravity-based: Heavy concrete structures using weight
- Best for: <10 meter shallow waters, clay/sandy soil seabeds
- Jacket/tripod: Frame of hollow steel tubes
- Best for: 50-70 meter medium depths, presents logistical issues
- Monopile: 3-8 meter wide poles driven into seabed
Vindeby Wind Farm Case Study (World's First)
- Location: 1.5-3 km off northwest coast of Lolland, Denmark
- June 1989: Elkraft power company demonstration project with 11 turbines
- Water conditions: 3-5 meter depths (too shallow for ships, too deep for construction machinery)
- Seabed: 10-meter clay layer topped with thin sand layer
- Foundation choice: Gravity-based concrete caissons
- 14 meters wide, 60 cm thick walls
- Weight: 710-1,105 tons each (equivalent 320 female elephants)
- Built to stand 2.5 meters above water line
- Installation process:
- Caissons floated to site using custom catamaran-like pontoon with tugboats
- Jack-up barge lifted/placed pre-assembled turbine pieces
- Jack-up barges: boats with vertical legs, float then stand up out of water
- Technology borrowed from oil industry offshore platforms
- Project outcome: Came in 3 million Danish kroner under budget
- Weather challenges: Limited working time, recommended 2-4 AM start when waters calmest
Modern Installation Evolution
- Larger turbines require bigger boats for scaling
- Custom-built jack-ups: >100 meters long, carry multiple turbines per day, much higher cost
- Installation procedures vary by foundation type:
- Monopile/jacket: hammered into ground (noise concerns)
- Gravity: seabed cleaning required, dig 1-meter hole, add 40 cm crushed stone layer
- Cable laying for grid connection
- Distant farms may use high voltage DC cables (higher converter costs but cheaper cables, lower transmission losses)
- Installation: ~6% of wind farm's total lifetime capital expenditure despite huge design importance
Reliability and Maintenance Challenges
- Environment: Violent squalls, corrosive salt water
- Lifespan requirement: 25 years with minimal maintenance
- Access issues: Cannot drive truck to site, long downtime during bad weather
- Maintenance costs: 2-3x higher than onshore equivalents
- Most frequent failure: Gearbox (raises blade speed for power generation)
- Highly mechanical, subjected to extreme physical conditions
- Difficult to replace, requires expensive jack-up barges
Global Leadership and Taiwan's Development
- European leaders: UK, Denmark leverage North Sea oil experience
- Taiwan's motivation: Diversify from fossil fuels
- 2020 Taiwan energy mix: 60% coal and natural gas
- Tai Zhong power plant: World's 4th largest coal-fired plant by generation capacity
- Challenges: Air pollution, climate change, nuclear power controversy, lack of buildable space
- Taiwan Strait advantages: Some of world's best offshore wind sites, highest wind speeds over past 9 years
Taiwan's Offshore Wind Projects
- Formosa One: Taiwan's first offshore wind farm
- 11 square kilometers, 6 km off Miaoli County coast
- Three-phase government plan:
- Phase 1: Two demo units by 2020
- Phase 2: 5.7 gigawatts capacity by 2025
- Changhua wind farm: Second demo (seen en route to Taichung), unfinished due to red tape, environmental concerns, local opposition
Floating Wind Turbine Technology
- Original concept: Dr. Heronimus's floating turbine vision
- Advantages: Deep water portability, pre-assembly on land, dragable to sea, removable after 25-year lifespan
- Disadvantages: Instability from pitching/rocking waves, unpredictable power generation efficiency
- Development status: Not yet production-ready, competing design concepts
- Spar buoy design:
- Closed cylinder floating upright under sea surface, tied to seabed
- Multiple cylinders for stability/wave resilience
- 2009: First Hywind demo in Norway
- 2017: Hywind Scotland (first floating wind farm)
- Tension-legged platform: Floating platform under surface, anchored with slim tension legs/tendons
- Derived from petroleum industry offshore oil rigs
- Widely proposed but limited demos exist
Industry Evolution and Future
- Vindeby retirement: 2017 after 25 years operation (world's first offshore wind farm)
- Denmark's expansion: 1995 second wind farm (Tunø Knob), now 15 offshore wind farms with more planned
- Global expansion: Netherlands, Sweden, UK leading offshore wind projects
- Competitiveness questions: Substantial subsidies suggest currently not competitive vs solar
- Improvement trends: More experienced builders, bigger turbines for economies of scale
- Hornsea wind farm: Massive scale example
- European hints: Some countries showing signs of subsidy-free competitiveness
- Technology assessment: Young but rapidly moving technology worth monitoring