South Africa’s Crumbling, Corrupt Electricity Monopoly

Asianometry

29m 27s

Early History and Foundation (1882-1922)

  • First electric lights in Kimberley 1882, 2 years after incandescent lamp invention
  • Arc lamps installed Table Bay docks extended working hours
  • Various cities installed street lights via small municipal utilities
  • Mining industry drove rapid growth, especially Witwatersrand gold fields
    • World's largest known gold reserves
    • 34,000 tons of 82,000 tons global gold (6,000 years to 21st century) came from Transvaal Province/Orange Free State
    • Gold fields dipped 60° angle, forcing deeper mining
    • 1899: deepest shaft 1,100m, by 1910: 1,850m
  • Fixed gold prices (currency tied to gold) forced automation to combat rising costs
  • Victoria Falls Power Company monopolized electricity supply to gold miners
  • WWI industrialization created labor shortages, state coordination increased
  • South African Railways wanted electrified trains, centralized state electricity provider

Eskom Formation and State Capitalism Era (1922-1948)

  • Electricity Act of 1922 created Electricity Supply Commission (Eskom)
  • Mandate: supply electricity to railways, government, industry at lowest cost
  • Cannot make profit/loss, exempt from income tax, raised capital via bonds
  • Government owned, light political oversight
  • State capitalism vision: diversify economy away from mining
  • Founded Industrial Development Corporation (IDC) 1928, Sasol oil-from-coal company
  • 1932: South Africa left gold standard, devalued currency
  • Gold prices/profits soared, electricity consumption grew 5x (1933-1948)
  • 1948: Eskom purchased Victoria Falls Power Company, consolidated power industry

Apartheid Era First Half - Growth Period (1948-1970s)

  • 1948: National Party won election, implemented apartheid
  • Economy grew well initially due to:
    • Bretton Woods system guaranteed stable gold prices
    • Low labor wages from apartheid policies
    • Import substitution industrialization
  • Local content in boiler/steam plants: 0% (1933) → 50% (1950) → 85% (1968)
  • Early power shortages 1949-1951 due to insufficient capacity, coal sourcing disputes
  • Load shedding implemented to prevent grid collapse
  • US Export-Import Bank and World Bank lent tens of millions for new power stations
  • Located near high-quality, shallow coal fields with cheap exploited labor
  • By 1960: provided world's cheapest power

Apartheid Era Second Half - Crisis and Expansion (1970s-1980s)

  • 1971: Nixon ended Bretton Woods, freed gold prices
  • 1974: Gold surged to 5x 1968 prices
  • Oil crises made electricity attractive, peak loads grew 6-16% annually (1972-1982)
  • Reserve margin fell to 11% (1975)
  • 1976: Soweto Uprising, political isolation increased
  • Massive coal plant building spree for energy independence
  • 1983: 11 GW generating capacity, 22 GW on order
  • Problems with expansion:
    • Increasingly larger plants (440 MW 1950s → 3,600 MW 1980s)
    • High interest expenses, long lead times, engineering inflexibility
    • Koeberg nuclear plant: framatome design, delays, cost overruns (0.5 billion rand)
  • Gold boom ended: peak $850/ounce (Jan 1980) → $340/ounce (1982)
  • Rate increases 20% (1976-1977) during economic difficulty
  • 1983: de Villiers Commission formed, found governance issues, renamed to Eskom

Democratic Transition and Policy Confusion (1990s-2000s)

  • 1989: FW de Klerk promoted deregulation/privatization
  • 1992: Reserve margin 40%, world's lowest generation costs
  • Long-term energy deals (up to 25 years) with mining companies, aluminum smelters
  • 1994: ANC won election, inherited Eskom serving mainly mining/white areas
  • 62% homes, 86% schools unconnected
  • 1994-2004: Added 2.4 million households to grid
  • 1996: Ate up all spare capacity due to electrification + economic growth
  • 1998: Government prevented new plant construction, wanted 30% private sector power by 2004
  • Plan to unbundle Eskom, create Regional Electricity Distributors
  • Only corporatization completed: became Eskom Holdings, required to pay corporate taxes
  • 2004: Finally allowed to build again, but too late
  • Demand grew 30% faster than supply (1997-2005), reserve margin fell to 8%

The 2008 Crisis and Mega-Project Disasters

  • January 2008: Heavy rains turned coal to sludge, nationwide blackouts
  • Had switched to lesser-known (mostly black-owned) coal suppliers, kept low stocks
  • Economy lost 2 billion rand/day during global commodity boom
  • Aging 1970s/1980s plants needed maintenance/replacement
  • Lost institutional knowledge of power plant construction
  • Medupi and Kusile mega-projects became boondoggles:
    • 2005 estimate: 93 billion rand ($14.5 billion) for 4 new plants
    • Each plant ~4.8 GW capacity
    • Scheduled operational 2012-2013
    • Actual completion: Medupi 2021 (14 years), Kusile still under construction
    • Final cost: 307 billion rand ($21 billion) public + $4 billion capitalized interest = $25 billion total
    • Coal plants cost equivalent to TSMC fab

Corruption and Criminal Infiltration

  • Endemic corruption via inflated contracts, kickbacks
  • 2019: Andre de Ruyter appointed CEO, served 3 years
  • Company 80% reliant on dirty, aging coal plants
  • Lack of scheduled maintenance, crappy coal input
  • Revenue problems: Municipal distributors marked up power, restricted rate increases
  • Trouble collecting payments from distributors
  • Debt spiral: borrowing to pay interest on existing debt
  • Criminal syndicates (up to 4) infiltrated company
  • Theft of coal, copper, materials: up to 1 billion rand ($55 million) monthly
  • December 2022: de Ruyter resigned, poisoned with cyanide after drinking coffee
  • Explosive interview accusing high-level ANC politicians of involvement

Recent Crisis and Recovery Attempts (2020s)

  • 2023: Record 330+ days of load shedding
  • Hot temperatures hit from both sides: increased AC demand, coal plants struggled
  • Stage 6 load shedding: 6,000 MW cuts, 8-10 hour daily blackouts
  • Government declared state of emergency, took on 14 billion debt
  • ANC lost absolute majority 2024 election for first time
  • Recovery plan:
    • Finish Medupi/Kusile final units
    • Add cheap renewables capacity
    • Incentivize private power generation (rooftop solar)
  • 2024: 10 months without load shedding but 25 billion rand ($1.36 billion) loss
  • Total debt: 400+ billion rand ($25 billion)
  • Forecast: Titanic power shortfall next 25 years from rising demand, retiring coal plants

TwinMind

Get summaries like this for your own meetings

TwinMind takes notes in the background during meetings, lectures, and calls, then writes the summary for you.

Free plan to get started

No bot joins your calls

Phone, desktop & Chrome apps

Your next meeting, summarized like this

TwinMind listens in the background and turns meetings, lectures, and calls into searchable notes you can chat with. Start free.

Available on phone, desktop & Chrome

Your next meeting, summarized like this

TwinMind listens in the background and turns meetings, lectures, and calls into searchable notes you can chat with. Start free.

Available on phone, desktop & Chrome

Your next meeting, summarized like this

TwinMind listens in the background and turns meetings, lectures, and calls into searchable notes you can chat with. Start free.

Available on phone, desktop & Chrome