South Africa’s Crumbling, Corrupt Electricity Monopoly
Asianometry
29m 27s
Early History and Foundation (1882-1922)
- First electric lights in Kimberley 1882, 2 years after incandescent lamp invention
- Arc lamps installed Table Bay docks extended working hours
- Various cities installed street lights via small municipal utilities
- Mining industry drove rapid growth, especially Witwatersrand gold fields
- World's largest known gold reserves
- 34,000 tons of 82,000 tons global gold (6,000 years to 21st century) came from Transvaal Province/Orange Free State
- Gold fields dipped 60° angle, forcing deeper mining
- 1899: deepest shaft 1,100m, by 1910: 1,850m
- Fixed gold prices (currency tied to gold) forced automation to combat rising costs
- Victoria Falls Power Company monopolized electricity supply to gold miners
- WWI industrialization created labor shortages, state coordination increased
- South African Railways wanted electrified trains, centralized state electricity provider
Eskom Formation and State Capitalism Era (1922-1948)
- Electricity Act of 1922 created Electricity Supply Commission (Eskom)
- Mandate: supply electricity to railways, government, industry at lowest cost
- Cannot make profit/loss, exempt from income tax, raised capital via bonds
- Government owned, light political oversight
- State capitalism vision: diversify economy away from mining
- Founded Industrial Development Corporation (IDC) 1928, Sasol oil-from-coal company
- 1932: South Africa left gold standard, devalued currency
- Gold prices/profits soared, electricity consumption grew 5x (1933-1948)
- 1948: Eskom purchased Victoria Falls Power Company, consolidated power industry
Apartheid Era First Half - Growth Period (1948-1970s)
- 1948: National Party won election, implemented apartheid
- Economy grew well initially due to:
- Bretton Woods system guaranteed stable gold prices
- Low labor wages from apartheid policies
- Import substitution industrialization
- Local content in boiler/steam plants: 0% (1933) → 50% (1950) → 85% (1968)
- Early power shortages 1949-1951 due to insufficient capacity, coal sourcing disputes
- Load shedding implemented to prevent grid collapse
- US Export-Import Bank and World Bank lent tens of millions for new power stations
- Located near high-quality, shallow coal fields with cheap exploited labor
- By 1960: provided world's cheapest power
Apartheid Era Second Half - Crisis and Expansion (1970s-1980s)
- 1971: Nixon ended Bretton Woods, freed gold prices
- 1974: Gold surged to 5x 1968 prices
- Oil crises made electricity attractive, peak loads grew 6-16% annually (1972-1982)
- Reserve margin fell to 11% (1975)
- 1976: Soweto Uprising, political isolation increased
- Massive coal plant building spree for energy independence
- 1983: 11 GW generating capacity, 22 GW on order
- Problems with expansion:
- Increasingly larger plants (440 MW 1950s → 3,600 MW 1980s)
- High interest expenses, long lead times, engineering inflexibility
- Koeberg nuclear plant: framatome design, delays, cost overruns (0.5 billion rand)
- Gold boom ended: peak $850/ounce (Jan 1980) → $340/ounce (1982)
- Rate increases 20% (1976-1977) during economic difficulty
- 1983: de Villiers Commission formed, found governance issues, renamed to Eskom
Democratic Transition and Policy Confusion (1990s-2000s)
- 1989: FW de Klerk promoted deregulation/privatization
- 1992: Reserve margin 40%, world's lowest generation costs
- Long-term energy deals (up to 25 years) with mining companies, aluminum smelters
- 1994: ANC won election, inherited Eskom serving mainly mining/white areas
- 62% homes, 86% schools unconnected
- 1994-2004: Added 2.4 million households to grid
- 1996: Ate up all spare capacity due to electrification + economic growth
- 1998: Government prevented new plant construction, wanted 30% private sector power by 2004
- Plan to unbundle Eskom, create Regional Electricity Distributors
- Only corporatization completed: became Eskom Holdings, required to pay corporate taxes
- 2004: Finally allowed to build again, but too late
- Demand grew 30% faster than supply (1997-2005), reserve margin fell to 8%
The 2008 Crisis and Mega-Project Disasters
- January 2008: Heavy rains turned coal to sludge, nationwide blackouts
- Had switched to lesser-known (mostly black-owned) coal suppliers, kept low stocks
- Economy lost 2 billion rand/day during global commodity boom
- Aging 1970s/1980s plants needed maintenance/replacement
- Lost institutional knowledge of power plant construction
- Medupi and Kusile mega-projects became boondoggles:
- 2005 estimate: 93 billion rand ($14.5 billion) for 4 new plants
- Each plant ~4.8 GW capacity
- Scheduled operational 2012-2013
- Actual completion: Medupi 2021 (14 years), Kusile still under construction
- Final cost: 307 billion rand ($21 billion) public + $4 billion capitalized interest = $25 billion total
- Coal plants cost equivalent to TSMC fab
Corruption and Criminal Infiltration
- Endemic corruption via inflated contracts, kickbacks
- 2019: Andre de Ruyter appointed CEO, served 3 years
- Company 80% reliant on dirty, aging coal plants
- Lack of scheduled maintenance, crappy coal input
- Revenue problems: Municipal distributors marked up power, restricted rate increases
- Trouble collecting payments from distributors
- Debt spiral: borrowing to pay interest on existing debt
- Criminal syndicates (up to 4) infiltrated company
- Theft of coal, copper, materials: up to 1 billion rand ($55 million) monthly
- December 2022: de Ruyter resigned, poisoned with cyanide after drinking coffee
- Explosive interview accusing high-level ANC politicians of involvement
Recent Crisis and Recovery Attempts (2020s)
- 2023: Record 330+ days of load shedding
- Hot temperatures hit from both sides: increased AC demand, coal plants struggled
- Stage 6 load shedding: 6,000 MW cuts, 8-10 hour daily blackouts
- Government declared state of emergency, took on 14 billion debt
- ANC lost absolute majority 2024 election for first time
- Recovery plan:
- Finish Medupi/Kusile final units
- Add cheap renewables capacity
- Incentivize private power generation (rooftop solar)
- 2024: 10 months without load shedding but 25 billion rand ($1.36 billion) loss
- Total debt: 400+ billion rand ($25 billion)
- Forecast: Titanic power shortfall next 25 years from rising demand, retiring coal plants