Unit 2: the Forecast is always wrong, Video 1: Cost Estimates

MIT OpenCourseWare

9m 54s

Introduction to Forecasting Problems

  • Topic: "The forecast is always wrong" (in quotes - acknowledges forecasts can match reality but rarely do)
  • Objective: Provide realistic assessment of forecasting ability accuracy
  • Evidence shows forecasts for system performance 5-15 years (or even 6 months-1 year for fast technology) differ substantially from actual outcomes

Runway Resurfacing Case Study - Simplest Technology Example

  • Analysis of ratio: real cost vs estimated cost
  • Graph shows percent of observations (0-15%) vs cost ratio
  • Perfect forecast would show ratio of 1.0
  • Results:
    • Range: 0.5 to 2.5 ratio (factor of 5 spread)
    • Median value: 1.25 (most frequent)
    • Ability to predict actual cost off by factor of 2 (half or double)
  • Process description:
    • Simple task: layer asphalt over runway after aircraft damage from repeated landings
    • Technology: drive truck, dump asphalt, roll down
    • Volume calculation straightforward: width × length × depth

Cost Variation Drivers

  • Energy prices major factor:
    • Oil prices varied from $15-$150 per barrel over 20 years
    • Factor of 8-10 variation
    • Affects asphalt, cement, steel production (energy-intensive processes)
    • Electricity price changes similarly
  • Labor cost changes:
    • High economic activity periods: overtime pay required
    • Recessions/bad economic times: low bids received
  • Conclusion: Largely driven by factors beyond control

General Project Cost Analysis

  • Survey of various project types (highways, ordinary activities)
  • Results:
    • Average cost vs predicted cost ratio up to 2.5
    • Standard deviation: ~0.5 (±50% variation)
    • Common experience: projected costs consistently under actual costs
    • Large variations both up and down

NASA High-Tech Project Analysis

  • National Aeronautics and Space Administration projects
  • High-tech, innovative, less usual activities
  • Results:
    • Cost variation much higher than ordinary projects
    • Many projects reached ~2× estimated cost
    • Standard deviation: >60%
    • More variation than standard projects

Key Conclusions

  • Forecasts consistently wrong across all project types
  • Not due to expert incompetence but world changes/external factors
  • Need to account for forecasting limitations in project estimation and management
  • Higher technology/innovation correlates with greater forecast uncertainty

TwinMind

Get summaries like this for your own meetings

TwinMind takes notes in the background during meetings, lectures, and calls, then writes the summary for you.

Free plan to get started

No bot joins your calls

Phone, desktop & Chrome apps

Your next meeting, summarized like this

TwinMind listens in the background and turns meetings, lectures, and calls into searchable notes you can chat with. Start free.

Available on phone, desktop & Chrome

Your next meeting, summarized like this

TwinMind listens in the background and turns meetings, lectures, and calls into searchable notes you can chat with. Start free.

Available on phone, desktop & Chrome

Your next meeting, summarized like this

TwinMind listens in the background and turns meetings, lectures, and calls into searchable notes you can chat with. Start free.

Available on phone, desktop & Chrome